…ar project content before the first build Verbatim copy of the Linear project's content field (2201 characters, updatedAt 2026-08-22T17:53:19.922Z), committed before the project-spec mirror overwrites it, so every fold-or-drop call is reversible. Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com> Claude-Session: https://claude.ai/code/session_01GmvuVRtAQQvxJfj4fMVirA
…ect spec First build, dispatched by FIX-1637's EPIC_SETUP. Four documents plus the territory and arc figures. Status derived from Linear: 2 epics done (FIX-1127, FIX-1157), 1 in flight (FIX-1503), 1 not started (FIX-1637). Absorbed from the prior Linear content: the original identity and the retracted-cuts list (now Decisions -> decided once, and the no-epic-may list). Left behind as stale: the 19-issue tier scope and its sequencing notes (that pass is done bar two extractions; summarized in PLAN). Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com> Claude-Session: https://claude.ai/code/session_01GmvuVRtAQQvxJfj4fMVirA
|
The latest updates on your projects. Learn more about Vercel for GitHub.
3 Skipped Deployments
|
…FIX-1637 direction merged FIX-1637 keeping flows alive moves to in flight (Spec Approved, 0/8, spec merged Sep 29 19:51 UTC as 2b6d67e). Arc redrawn: FIX-1637 bar starts at approval, FIX-1503 bar and the now line move to Sep 29 19:54. Counts re-derived from Linear: 66 open, 55 under no epic, 26 bugs. Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com> Claude-Session: https://claude.ai/code/session_01GmvuVRtAQQvxJfj4fMVirA
…FIX-2447 filed Status refresh only. The epics table, graph and arc now carry the four epics filed since Sep 29 (FIX-2036, FIX-2171, FIX-2316, FIX-2447); FIX-1637 moves to 4/8 and FIX-2316 shows as wrapped Oct 31. Counts re-derived from Linear: 80 open, 35 under no epic, 20 open bugs. Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com> Claude-Session: https://claude.ai/code/session_011UNkLC9NknMcaqpK1h2mVK
…FIX-2600 filed Adds the vocabulary epic (FIX-2600) to the epics table, graph and arc. Re-derives FIX-2447 (direction merged Nov 5, 2/20) and FIX-1637 (closure spec approved) from Linear. Arc rescaled to 7px/day so the now line fits. Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com> Claude-Session: https://claude.ai/code/session_011UNkLD7mJaky2QRikkQ8Z4
…K wraps Wrap update: FIX-2447 to done (32/33 in Linear, FIX-2638 canceled into FIX-2739); decided once 7-10 (no aliases, one summary line for removed root exports, install flag until FIX-2737, minor bump pre-1.0); PR-2 owned by FIX-2447; the FIX-2739 handoff seam to the docs revamp. Status refresh: rows for FIX-2618, FIX-2683, FIX-2696; FIX-2600 in flight; arc redrawn to Nov 15. Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com> Claude-Session: https://claude.ai/code/session_011UNkLC9NknMcaqpK1h2mVK
…ecisions, rules, plan, arc The rest of the wrap update (SPEC.md landed in the previous commit): decided once 7-10, PR-2, the FIX-2739 and FIX-2618 -> FIX-2683 seams, and the arc redrawn to Nov 15 with twelve lanes. Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com> Claude-Session: https://claude.ai/code/session_011UNkLC9NknMcaqpK1h2mVK
Code Review ✅ Approved 🟢 Low risk 1 closed / 1 findingsAdds project-spec, planning, and decision documentation without changing executable code or interfaces, so its direct behavior impact is limited. Review completed with no unresolved findings. ✅ 1 closed✅ Bug: DECISIONS.md still uses stale epic and issue counts that contradict SPEC/PLAN
VerificationRules No rules evaluated Functional validation Not enabledFor more verification details, comment OptionsAuto-apply is off → Gitar will not commit updates to this branch. Comment with these commands to change the behavior for this request:
Important Your trial ends in 4 days — upgrade now to keep code review, CI analysis, auto-apply, custom automations, and more. Was this helpful? React with 👍 / 👎 | Gitar |
This PR is where FSD fixes the places its surface says one thing and does another, or offers two of something where a builder needs one, before its public release. It is never merged; it stays open as the project's live surface.
The territory renders in SPEC.md (Files tab, or the branch blob view at head b4a1518).
The fence is one test: does the change make an existing statement true, or remove a second of something? A change that adds a capability belongs to another project.
The arc renders in PLAN.md (same place).
Two short closed bars in August, two long live ones since late September, then eight epics filed in four weeks. Clean SDK closed its bar on Nov 15, ten days after its direction merged.
The epics, as of 2026-11-15 00:50 UTC (head b4a1518): FIX-1127 declared surface, FIX-1157 durable storage, FIX-2316 mechanism sweep and FIX-2447 clean SDK, done · FIX-1503 verified identity, in flight (Linear still reads In Spec Review, its one child in Backlog) · FIX-1637 keeping flows alive, in flight (4/8) · FIX-2600 vocabulary, in flight (4/5) · FIX-2618 feature kits, in flight (10/13) · FIX-2696 docs revamp, in flight (3/9, carries clean SDK's leftovers in FIX-2739) · FIX-2036, FIX-2171 and FIX-2683, filed, not started. The live table is in SPEC.md.
Clean SDK wrapped, and settled four things siblings should read rather than reopen (DECISIONS.md → decided once 7–10): no backward-compat aliases; removed root exports get one summary release line with the count, checked exactly only on the Version Packages PR (BUSINESS-RULES.md → PR-2), so an epic that drops a root export edits no changeset until release; the install docs keep pnpm's
--allow-build=better-sqlite3until FIX-2737; removing root exports is aminorbump before 1.0.Open · one question for you (no gate)
Does this project end at the public release, or stay open as the standing cleanup bucket?
Plain terms. This was a three-week pass with a May 22 target, now done bar two package extractions. Since August it has become where "FSD says one thing, does another" fixes land: twelve epics, 100 open issues, 68 under no epic. Nothing says when it is finished.
The trade-off. Ending at the public release gives a finish line and forces one triage of the 68 (ship before release, move to Public Launch's hard gates, or move to a post-release project). A standing bucket costs nothing now but can never be called done.
My recommendation. End it at the public release; the surface is cheapest to make true before people build on it. Set the Linear target once the release has a date.
What would change my mind. A release a quarter or more away, where a narrower line ("the 28 bugs") is better; or cleanup already tracked another way you prefer.
What being wrong costs. Low and reversible: a date and a label.
Reviewers · look here
The set: SPEC.md · DECISIONS.md · BUSINESS-RULES.md · PLAN.md · absorbed/linear-content.md (the prior Linear content, verbatim), all under spec/_projects/framework-simplification-and-cleanup/ in this PR's Files tab · Linear project · never merged
How to review this — a project-spec, not an implementation plan
This is a project-spec: the standing outcome, the cross-epic decisions, and the live state of
one Linear project, in four documents. It is not an implementation plan, not any one epic's
objective, and not a design.
In scope to challenge:
That question can only be asked here.
DECISIONS.mdthat binds several epics, or a rule inBUSINESS-RULES.mdwith noowner or two.
Out of scope — owned by the epic specs below it:
the project moves and is never a review finding.
Feedback in the second list is routed to the epic it concerns, not folded in here.